Week 17 (August 21 – 25)

In my final week I was able to finally test, document, and finish the automation tool and put it into production. This was the major thing I worked on over the term and I really enjoyed so I’m glad it made it successfully into prod before I had to leave. I also made some changes requested by the data gen specialists to some other tools before leaving. It’s sad to leave Magnet, I really enjoyed this term and wish it could have gone on for longer. Nevertheless I look forward to graduating and coming back next May!

Week 16 (August 14 – August 18)

This week was mostly just tying up most of the side projects I was working on. So i was able to finish the provisioning tool work and some dashboard tickets as well as some other documentation and other minor things. Next week I plan on finish the automation tool. I’m also very happy to say that Magnet offered me a job and I accepted, so even though my work term ends next week, I’ll be back next May as a full time developer.

Week 14 (July 31 – August 4)

I finished the provisioning tool changes and they tested successfully, we’re just waiting for some time to train the users on the new functionality and UI. After talking to the data gen team we agreed that all the work I had done was god enough to be productionalized, even the parts that couldn’t be automated. So I’m now working on making the data gen automation project into a tool that given some configuration will run the specific data gen processes for each platform. I finished the config design this week, and will begin work on the actual tool next week.

Week 13 (July 24 – July 28)

My provisioning tool changes passed all the testing, however the users of the tool recommend some function and aesthetic changes, so I’ve been working on those in my spare time. Most of my recent work was with the dashboard and getting some of the automation project ready for production. Next week I plan on discussing everything with the data gen specialists next week to plan out how the automation job should work.

Week 10 (July 3 – July 7)

The testers found a couple odd bugs with the usb license tool that were somewhat challenging to fix. However I was able to repair the tool as well as add some recommended aesthetic changes. Both Windows and Mac automation projects are done, I just need to integrate them. Both of these platforms have their limitations unfortunately, so we’ll have to discuss what to do with these going forward. I’ve also been tasked with making changes to our internal usb provisioning tool which is more licensing work, which I’m excited about.

Week 9 (June 26 – June 30)

This week was a continuation of last week basically. I played around with some Mac and Windows automation and was able to implement some basic processes. Next week I plan on improving these and integrating them into the project. The testers have begun looking at the usb licensing tool so I’m waiting to hear back from them. I’ve also looked at some more dashboard tickets and have tried to learn some more about react and redux.