Week 20 (September 14 – September 18)

The first bug report came and as expected there was a lot of them. We do assume a lot of them are confusion about how BOL reconciliation works and its limitations so we’ve been tracking down a lot of those and grouping them together. There’s several meeting scheduled to explain the process to the testers and we’ve been having a lot of refreshers within the team about the algorithms involved. I’ve mostly been frantically tracking the cause of bugs and applying fixes. We also need to send out a daily status report of all the open bugs; Wednesday is my day to fill that out. The application finishes without any errors using the test files which is good, it’s just going to be a matter of fixing all the data errors.